The highly concerned "Huizhou Coastal Economic Belt Comprehensive Development Plan (2020-2035)" was formally approved by the municipal government for the implementation of the overall planning and construction of the coastal economic belt, creating a world-class petrochemical industrial base, and the Guangdong-Hong Kong-Macao Greater Bay Area Energy Technology Innovation Center. . Combining the natural attributes, spatial attributes, industrial foundation and development direction, the overall marine development pattern of "one corridor, one belt, three axes, and four groups" has been gradually constructed.
The petrochemical industry is one of Huizhou's two pillar industries. In recent years, it has proposed to build a trillion-level industrial cluster. To develop Huizhou's coastal industry, it is inseparable from the layout of the petrochemical industry. Among them, the petrochemical industry has been planned and distributed in the medium and long term. The details are as follows:
Make the petrochemical industry bigger and stronger
Accelerate the construction of ExxonMobil Huizhou Ethylene Project, Huizhou Petrochemical Phase III Refinery-Chemical Integration Project and other projects, and plan to build a new 10 million-ton/year refining-chemical integration project in the long-term. Strive to form an industrial scale of 32 million tons of oil refining, 6.1 million tons of ethylene and 3.1 million tons of aromatic hydrocarbons by 2028, and initially build a world-class green petrochemical industry cluster; by 2035, form an annual output of 42 million tons of oil refining and 7.6 million tons The industrial scale of ethylene and 3.1 million tons of aromatic hydrocarbons has been built into a world-class green petrochemical industrial base.
Key projects in the petrochemical industry
China Shipping Shell's SMPO/POD project. Newly build 6 sets of production equipment, which are 750,000 tons/year ethylbenzene, 630,000 tons/year styrene, 300,000 tons/year propylene oxide plant and 100,000 tons/year polymer polyether, 250,000 tons each 2 sets of polyether polyol devices per year. It is planned to be completed and put into operation in 2020.
CNOOC Huizhou Petrochemical Co., Ltd. product structure optimization and quality upgrade project. Including new 1.6 million tons/year hydrocracking unit, 1.5 million tons/year aromatics unit, 1.3 million tons/year continuous reformer and other production equipment, the total investment of the project is about 6.54 billion yuan, and it is expected to be completed and put into production in 2022.
Huizhou Petrochemical Phase III refining and chemical integration project. The total investment of the project is about 60.8 billion yuan, including the chemical and oil refining components. Among them, the chemical part is based on a 1.5 million ton/year ethylene cracking unit, with a total of 14 chemical plants; the oil refining part is based on the integration and optimization of the first and second phases of oil refining, with supporting transformation and moderate expansion of 5-8 million tons/year of refining capacity. 11 sets of devices.
ExxonMobil Huizhou Ethylene Project. The total investment of the project is about 10 billion US dollars, which will be constructed in two phases. The investment of the first phase project is about 34.2 billion yuan, and a 1.2 million ton ethylene/year crude oil direct cracking olefin production unit, 1.2 million ton/year high performance polyethylene unit, 850,000 ton/year high performance polypropylene unit and by-products and storage Supporting facilities related to transportation and public works.
Long-term planning projects. Planning and construction of an integrated refining and chemical project of 10 million tons/year of oil refining and 1.2 million tons/year of ethylene, with the fundamental goal of improving quality and efficiency, and improving the overall development quality of the park, with chemical as the core, mutual supply of oil refining and chemical products, as far as possible Reduce product oil production. Or construct two sets of 1.2 million tons/year ethane cracking unit and two sets of 600 thousand tons/year propane dehydrogenation unit to produce ethylene and propylene.
Do deep and do fine petrochemical new material industry
In accordance with the overall thinking of "overall planning, step-by-step implementation, key development, and rational layout", relying on the existing oil refining and ethylene foundation, the product chain will be extended downstream to build a series of high-end new chemical materials projects. Planning and construction of Huidong New Material Industrial Park, vigorously develop petrochemical downstream industries such as new chemical materials and high-end chemicals, and do a good job in deepening the long petrochemical industry chain. Strive to reach the output value of 200 billion yuan for new chemical materials and high-end chemicals by 2035.
Key development direction of new chemical materials and high-end chemicals
High-performance synthetic materials. High-end polyolefin, engineering plastics, high-performance synthetic rubber, 3D printed plastic materials, polyurethane, kinetic energy film, etc.
High-end chemicals. Coatings, chemical additives, water treatment agents, electronic chemicals, adhesives, special chemicals, feed additives, food additives, bio-based chemicals, etc.
High performance fiber. Aramid, carbon fiber, ultra-high molecular weight polyethylene fiber, polyphenylene sulfide fiber, polyimide fiber, polyparaphenylene benzodioxazole fiber (PBO), silicon carbide fiber, continuous basalt fiber, etc.
Improve petrochemical industry service packages
Benchmark the world-class petrochemical park, upgrade the infrastructure of Daya Bay Petrochemical Zone, and comprehensively upgrade and renovate facilities such as road traffic, wharf channels, security communications, and emergency rescue.
Promote the expansion and quality improvement of warehousing and logistics facilities.
Do a good job in reclamation and land reclamation, energy conservation and environmental protection, and create space for industrial development.
Actively build an innovation and financing public service support platform, vigorously introduce leading technology talents and innovation teams, and plan to build an international level petrochemical technology R&D center.
Accelerate the planning and construction of Huidong Baihua New Material Park, increase investment in industry chain investment selection, build and complete supporting facilities such as dedicated passages, flood drainage and sewage pipeline corridors.
Source: Mobei Public Account