The Total Investment Is About 67.7 Billion Yuan! The First Batch Of Core Equipment Of Shenghong Refining And Chemical Integration Project Was Successfully Delivered

Jul 02, 2021

Leave a message

On June 30, in the Xuwei New District of Lianyungang, Jiangsu, the construction of the Shenghong Refining and Chemical Integration Project, which is the largest in China in terms of single-process scale, made key progress. The intermediate delivery of the first batch of main production equipment such as atmospheric and vacuum distillation was successfully completed and officially transferred to Preparation stage for production.


It is understood that the first batch of equipment delivered this time includes the project’s core main equipment atmospheric and vacuum distillation equipment, sulfur recovery equipment, naphtha hydrogenation equipment, IGCC combined equipment (PSA unit), as well as supporting crude oil tank farms and public utilities. Engineering systems, storage and transportation systems, environmental protection devices, and system pipelines. The first batch of core devices achieved the CCCC goal as scheduled, laying a solid foundation for the commissioning of the project at the end of this year.


The Shenghong Refining and Chemical Integration Project is a key project of the national "Petrochemical Industry Planning and Layout Plan", with a total investment of about 67.7 billion yuan and a crude oil processing capacity of 16 million tons per year. After it is completed and put into production, it will refresh the single process scale of my country's refining and chemical projects. Record. The project adopts international leading technology and equipment, and the core equipment has set many firsts in China. Among them, the 16 million tons/year atmospheric and vacuum distillation unit and the wax oil hydrocracking unit are the largest in China. The kerosene hydrogenation unit is designed according to the two working conditions of aviation kerosene and diesel. The production arrangement can be dynamically adjusted according to the demand of the refined oil market. , The market competitiveness is further enhanced; the para-xylene plant is the first to introduce a two-stage heavy-slurry recovery process in China, and it is currently the world’s largest single-series para-xylene plant; the project also has the largest domestic continuous process technology in China. Complete equipment-2 sets of 3.5 million tons/year continuous reforming equipment, realizing the complete autonomy of key technologies.


As the leading project of the Lianyungang National Petrochemical Industry Base, after the completion of the Shenghong Refining and Chemical Integration Project, it will plan to realize more than 80% of the raw materials and products in the base to form a complete closed loop of the high-end petrochemical industry chain, which is conducive to expanding domestic demand, Reduce the petrochemical industry’s dependence on the international market, and accelerate the formation of a “dual cycle” pattern of my country’s petrochemical industry at home and abroad.


Focusing on the goal of carbon peak, carbon neutrality and "dual carbon", Shenghong Refining & Chemical takes the concept of "environmental protection first and green development" as the most important goal and positioning of the project, and invests in strict accordance with the highest standards in safety and environmental protection, and will never compromise . The project’s investment in safety and environmental protection reached 11 billion yuan, accounting for 16% of the total investment. It is at the industry’s leading level, laying a solid foundation for the project’s green, low-carbon, and safe operation; the water system adopts advanced circulating water mist-eliminating cooling technology, which is compared with conventional equipment Water saving is 12.8%, and water saving is about 4.9 million tons/year, which is equivalent to the water consumption of about 40,000 households in a year. Through overall process optimization, the water reuse rate of Shenghong Refining and Chemical Project reaches 85%, which is higher than that of ordinary projects. 15%.


Shenghong Refinery pays attention to the recycling and utilization of the "three wastes" in the process, implements the recycling economy concept of waste reduction and resource utilization, and through the thermal integration of the entire plant, the low-temperature heat, combustible gas and oil and gas are recycled and utilized to achieve power. The system is used step by step, greatly reducing energy consumption and emissions. The innovative use of a refrigeration compressor and an ethylene tower to form a heat pump system in the ethylene plant can save energy by nearly 15% and reduce CO2 emissions by 2 million tons per year, which is equivalent to planting 20 million trees. In the past two and a half years since the start of construction, the Shenghong Refining and Chemical Integration Project has grown from a barren beach to a large number of "big powers", bursting out the "strongest voice" of Jiangsu coastal development. On June 30, in the Xuwei New District of Lianyungang, Jiangsu, the construction of the Shenghong Refining and Chemical Integration Project, which is the largest in China in terms of single-process scale, made key progress. The intermediate delivery of the first batch of main production equipment such as atmospheric and vacuum distillation was successfully completed and officially transferred to Preparation stage for production.


It is understood that the first batch of equipment delivered this time includes the project’s core main equipment atmospheric and vacuum distillation equipment, sulfur recovery equipment, naphtha hydrogenation equipment, IGCC combined equipment (PSA unit), as well as supporting crude oil tank farms and public utilities. Engineering systems, storage and transportation systems, environmental protection devices, and system pipelines. The first batch of core devices achieved the CCCC goal as scheduled, laying a solid foundation for the commissioning of the project at the end of this year.


The Shenghong Refining and Chemical Integration Project is a key project of the national "Petrochemical Industry Planning and Layout Plan", with a total investment of about 67.7 billion yuan and a crude oil processing capacity of 16 million tons per year. After it is completed and put into production, it will refresh the single process scale of my country's refining and chemical projects. Record. The project adopts international leading technology and equipment, and the core equipment has set many firsts in China. Among them, the 16 million tons/year atmospheric and vacuum distillation unit and the wax oil hydrocracking unit are the largest in China. The kerosene hydrogenation unit is designed according to the two working conditions of aviation kerosene and diesel. The production arrangement can be dynamically adjusted according to the demand of the refined oil market. , The market competitiveness is further enhanced; the para-xylene plant is the first to introduce a two-stage heavy-slurry recovery process in China, and it is currently the world’s largest single-series para-xylene plant; the project also has the largest domestic continuous process technology in China. Complete equipment-2 sets of 3.5 million tons/year continuous reforming equipment, realizing the complete autonomy of key technologies.


As the leading project of the Lianyungang National Petrochemical Industry Base, after the completion of the Shenghong Refining and Chemical Integration Project, it will plan to realize more than 80% of the raw materials and products in the base to form a complete closed loop of the high-end petrochemical industry chain, which is conducive to expanding domestic demand, Reduce the petrochemical industry’s dependence on the international market, and accelerate the formation of a “dual cycle” pattern of my country’s petrochemical industry at home and abroad.


Focusing on the goal of carbon peak, carbon neutrality and "dual carbon", Shenghong Refining & Chemical takes the concept of "environmental protection first and green development" as the most important goal and positioning of the project, and invests in strict accordance with the highest standards in safety and environmental protection, and will never compromise . The project’s investment in safety and environmental protection reached 11 billion yuan, accounting for 16% of the total investment. It is at the industry’s leading level, laying a solid foundation for the project’s green, low-carbon, and safe operation; the water system adopts advanced circulating water mist-eliminating cooling technology, which is compared with conventional equipment Water saving is 12.8%, and water saving is about 4.9 million tons/year, which is equivalent to the water consumption of about 40,000 households in a year. Through overall process optimization, the water reuse rate of Shenghong Refining and Chemical Project reaches 85%, which is higher than that of ordinary projects. 15%.


Shenghong Refinery pays attention to the recycling and utilization of the "three wastes" in the process, implements the recycling economy concept of waste reduction and resource utilization, and through the thermal integration of the entire plant, the low-temperature heat, combustible gas and oil and gas are recycled and utilized to achieve power. The system is used step by step, greatly reducing energy consumption and emissions. The innovative use of a refrigeration compressor and an ethylene tower to form a heat pump system in the ethylene plant can save energy by nearly 15% and reduce CO2 emissions by 2 million tons per year, which is equivalent to planting 20 million trees. In the past two and a half years since the start of construction, the Shenghong Refining and Chemical Integration Project has grown from a barren beach to a large number of "big powers", bursting out the "strongest voice" of Jiangsu coastal development.

Send Inquiry