Qixiang Tengda recently disclosed the progress of MMA and propylene oxide projects on the investor interaction platform. The company expects that multiple fine chemical projects will be completed and put into production in 2021, and the company's production capacity will be effectively expanded.
According to reports, as of now, the civil foundation construction of the main device of the 200,000-ton/year MMA project has been basically completed, the main steel structure of the main device has been completed, and the process piping has been 90% completed. The compressor plant is undergoing wall panel construction. The incinerator manufacturer The equipment is being installed, and the refined acid unit is under construction of equipment and steel structure. In terms of equipment installation, 4 German reactors have been put in place, and the construction of the head and external equipment is in progress. The installation of the remaining equipment has been completed 80%. If it goes well, the project is planned to be completed and put into production before the end of March 2021.
The 300,000-ton/year propylene oxide project is organizing a long-term technical exchange of equipment; the project has completed the project establishment, energy assessment, and environmental assessment, and has obtained relevant approvals, and is stepping up the procedures for safety assessment. The detailed design of the design institute is being carried out in an orderly manner, the auxiliary building drawings have been designed, and the non-standard equipment and the final flow chart are being designed.
The order for large equipment and static equipment of the 700,000 tons/year propane dehydrogenation project has basically been completed 90%, small equipment is being inquired, and the pipes are expected to be delivered by the end of January 60%-90%. Part of the basic drawing design has been completed, and construction has begun on site; the construction of the pipe gallery foundation and frame in the device has reached 50%; the heating furnace design has been completed, and the construction completion rate is about 60%; the rectification unit tower is being prefabricated on site, and the foundation and frame are expected Construction in the near future. If it goes well, the project is planned to be completed and put into production before the end of 2021.
The 200,000 tons/year isononanol project patent licensor is making process packages and delivering them to the company in batches. The project approval has been completed, and the energy assessment, environmental assessment and safety assessment reports are being prepared. At the same time, it is working with the design institute to dock the drawing design work.